Pre Commission Service
As part of a new service to simplify installing charge points Park & Recharge offered to pre-commission the charging infrastructure prior to installation.
Dynamic Demand Controller
The installer’s site survey showed that the peak demand is 195kVA. As such they could not use all four 100kw rapid chargers at full capacity without causing a power failure.